Okay Matt:

One more thing, as you can see, we ran short on the shakes for the upstairs. We are not getting our delivery of the balance of the materials until Wednesday….Can you please call the canopy people and reschedule them for next week Thursday or Friday? As we will not have that last part of the peak done before the Wednesday installation. I apologize for the inconvenience.

Ray would like the screen door left off until all the work is done, as we do not want drips of paint or mud from the joint compound to embed itself in the screening. He will take care of putting it in place. He feels confident that the door was made properly.

Phyllis and I could come by on Thursday at 4:00 so you can look at the paint boards and give your approval. Let me know that this works for you.

Schedule this week: Electrical Monday and Tuesday

Inspection on Wednesday

Patching on Thursday along with finish up of outside work

Begin painting work on Friday

Next week: Wallpaper removal, priming painting, etc……This will take all week

Regards,

Jill

From: Jill Doss [mailto:jdoss@gsigranite.com]
Sent: Monday, May 11, 2009 1:46 PM
To: 'Matthew Piette'
Subject: FW: Work for tomorrow, 5.7.09

Matt:

The electricians will be back tomorrow. Could you please mark on the West wall in the bar in basement, where you would like the cable (ideally) placed? They can then determine what work may be needed to provide service to that area.

Also, the three switch box (to control the recessed lights) will need to be moved to a location directly below the phone. The wall immediately to the left, as you walk into the family room, has a large, brick support directly behind the wall, which prohibited installation of the box at the location we had originally planned on. Switches need to be within a certain amount of a doorway so they can be turned on easily when entering the room. Placing the switch under the small niche area (where we would have finally had room) would have been over too far for code.

We are able to install the outlet over to the right, and above the heat registers, along the desk wall

As discussed, the one 6” recessed light will be moved over to be centered above the desk area.

Also, your phone jack on the kitchen doorway was found to be on its’ last legs (discovered when installing the new switch box below). I gave the electricians the go-ahead to replace it. Hope that is okay.

All for now…..

Jill